75 KLD CAMUS-SBT Based STP at HSIL Hindware, Hyderabad (Telangana)

 

Scale of service

Institutional

Area of installation
(Sq-m)

82.2 Sq-m

Year of Installation

August 2020

Capital cost

Rs. 44.0 Lakhs

Location

Isnapur, Hyderabad

Operational & Maintenance cost

Rs. 2 Lakhs per annum

Implementing & Funding Agency

HSIL Hindware

Design Capacity

75 KLD

 
 

This sewage treatment plant has been designed for the wastewater coming from the HSIL factory where nearly 600 employees work in the premises.

 
 

The sewage from the facility after preliminary screening gets collected to Raw Sewage Tank (RST) for collection and equalization. The raw water is been pumped to Bio Mound 1 (BM1) via the piping network in BM1 which enables equal distribution of sewage throughout the reactor surface area. The sewage distributed in BM1 gets trickled down by gravity in Collection Tank 1 (CT1). Similarly, the water in CT1 gets pumped to Bio Mound 2 (BM2) which gets treated and collected in Collection Tank 2 (CT2). The water in the CT2 Tank is the treated water and hence CT2 is named as Treated Water Tank (TWT).

 
 

Plant is able to achieve sustained results in terms of removal efficiency; TSS( >85%), BOD(>85%) & COD (>85%). The treated water is odour and colour free.

 
 

Mr. Anil Ravi
Phone No 9030706796
Email Id anilravi@hindware.in

Address: HSIL, Hindware Isnapur, District, Sanga Reddy Telangana
Website https://www.truflopipes.com/

For Vision Earthcare Pvt Ltd

Mr. Mohit Hariya
Designation Maintenance Manager
Email Address maintenance@visionearthcare.com
Phone No. +91 7304540858

 

 

Tags: