Key Highlights of the Projects | |||
Year of Commission
|
2016 |
||
Total Installed Capacity
|
7 MLD |
||
Total Utilization Capacity
|
6.5 MLD | ||
Treatment Technology | Moving Bed Biofilm Reactor | ||
Current Reuse | Irrigation Purpose | ||
Volume of Water Reuse Daily | 1.25 MLD | ||
Quality of treated water (Outlet) | pH- 7.93. BOD-9mg/l, COD-40mg/l, TSS-14mg/l | ||
Economics | NA | ||
Current Reuse Practice Horticulture and green belts | |||
• A 27.5 kW solar power plant operates pumps for 6 hours daily, providing sustainable energy. • The project utilizes 1.25 MLD of treated water to irrigate 156 acres of farmland, benefiting 37 farmers. • The total project cost is approximately ₹90 lakh, covering infrastructure, distribution, and solar plant installation. • Surplus treated water is discharged into the Rakshi drain, 1.25 km from the plant. Surveys are underway to extend the project to Jainpur Jattan and Barhan villages, with implementation planned for March 2024. |
|||
Share this article