Feb 20, 2012
Asks project proponent to obtain environmental clearances
The National Green Tribunal has put on hold the Bhadreshwar thermal power plant at Mundra in Gujarat. It has asked the project proponent, OPG Power Gujarat Pvt Ltd, to stop all works at its 300 MW power plant till it gets the requisite environmental clearance.
"We have no hesitation to hold that until OPG Power Gujarat Pvt Ltd obtains clearance to use reserve forest land and clearance from the Coastal Regulation Zone Authorities, it cannot go ahead with the project," said a bench comprising chairperson A S Naidu and Vijai Sharma on February 14.